The Boiler Quotation: What It Must Contain to Win the Order
What a boiler quotation should contain: technical particulars, HSN and GST by place of supply, payment milestones, scope, exclusions, delivery and warranty.
4 min read
By the Yantra Boilers team

Key takeaways
- The buyer's purchase team compares quotations line by line: technical particulars, scope and exclusions matter as much as the price.
- GST follows the place of supply: CGST and SGST for a buyer in your state, IGST for another state, and a zero-rated export for a buyer abroad.
- State payment milestones in rupees as well as percentages, tied to events both sides can see: the PO, dispatch, commissioning.
- Never edit a sent quotation. Issue a revision with the same number, so nobody accepts a price you have withdrawn.
A boiler quotation is read by more people than the one who asked for it. The plant head checks the capacity and fuel, the purchase manager compares prices and terms, the accountant checks GST, and sometimes a consultant reads the technical particulars line by line. A quotation that answers all of them, clearly, is the one that is easy to approve.
Letterhead, buyer and reference
- Your company name, address, phone, email, GSTIN and the approvals you hold.
- A quotation number and a revision number, the date, and how long it is valid.
- The buyer’s company, the person it is addressed to, their address and GSTIN.
- A subject line that names the boiler: “Offer for a 2.5 TPH rice husk fired steam boiler”.
Technical particulars
Before the price, set out what the buyer is getting: equipment type, actual output and the from-and-at-100 °C rating, working and design pressure, fuel and its calorific value assumed, efficiency, heating surface, feed water temperature, and the main dimensions. If the buyer gave you their load, say what the offer assumes about it, so a wrong assumption is caught now and not at commissioning.
Price, HSN and GST
List each item with its HSN code, quantity, unit, rate and amount. Steam boilers come under HSN heading 8402; for heaters, accessories, spares and services, confirm the code and rate with your accountant. GST then follows the place of supply:
| Buyer | Tax shown |
|---|---|
| In your state | CGST and SGST, half the rate each |
| In another state | IGST at the full rate |
| Outside India | Export: zero-rated supply |
Round the grand total to the rupee and show the round-off, and write the total in words the Indian way: “Rupees Twenty Eight Lakh Ninety One Thousand Only”.
Payment terms
Tie each payment to an event both sides can see, and state it in rupees as well as a percentage. A common pattern is an advance with the purchase order, the main payment before dispatch against a proforma invoice, and a balance after commissioning. Whatever yours is, the amounts must add up to the total exactly.
Scope of supply and exclusions
Most disputes after an order come from scope, not price. List what you supply: the boiler with its mountings and fittings, feed pumps, fans, the control panel, chimney if included, drawings, test certificates and manuals. Then list what you do not: civil work, the water treatment plant unless included, piping beyond your terminal points, cabling to your panel, unloading at site, and statutory fees.
Terms
- Price basis: ex-works or delivered, and whether packing is included.
- Delivery: in weeks from the later of drawing approval and the advance.
- Freight: included, extra at actuals, or by the buyer’s transporter.
- Erection and commissioning: supervised by your engineer, with who pays for travel and stay.
- Warranty: its period and start, and what it does not cover, such as refractory and consumables.
- Validity: a date, after which the price must be confirmed again.
Revisions
Negotiation means a second and third price. Never change a quotation the buyer already has: issue a revision with the same number, R2, and withdraw the earlier one. Otherwise sooner or later someone places an order against an old price.
Sending it
A link the buyer opens on a phone, prints to PDF for the file, and accepts with their PO number shortens the time from offer to order. Knowing it was opened yesterday tells your engineer when to call.
Common mistakes
- Charging IGST to a buyer in your own state, or CGST and SGST to one in another.
- Payment percentages that do not add up to 100, or amounts that do not add up to the total.
- A scope of supply copied from another boiler, listing equipment this one does not include.
- No validity date, so a buyer places an order months later at an old price.
- Technical particulars that disagree with the price section about capacity or fuel.
Once the quotation is accepted, the same details become the order: the payment plan turns into milestones in rupees and the buyer follows each stage on a link.

Following up
A quotation sent and forgotten is a quotation a competitor wins. Call the buyer a day or two after they open it, ask what they are comparing, and offer to walk their engineer through the technical particulars. Knowing when it was opened tells you when that call will be welcome.

When the buyer changes the requirement
It is common for a buyer to come back after the first offer with a different capacity, a second fuel, or a request to add the water treatment plant. Treat it as a new revision, not a correction: change the technical particulars and the lines together, check the scope and exclusions still match, and send the revision with a short note saying what changed and why the price moved. Buyers comparing three makers read revisions closely, and a revision that explains itself is easier to approve than one that only shows a new total.
Keep every revision on record, numbered, with the date it was sent. When the purchase order arrives, it should name the revision it accepts, so there is never a question about which price and scope were agreed.
Frequently asked questions
- What is the HSN code for a steam boiler?
- Steam boilers fall under HSN heading 8402. Confirm the full code and GST rate for each item, especially heaters, parts and services, with your accountant.
- When is IGST charged instead of CGST and SGST?
- When the place of supply is in a different state from yours. A buyer in your own state pays CGST and SGST at half the rate each.
- How long should a boiler quotation be valid?
- Long enough for the buyer’s approval cycle and short enough that steel prices have not moved: 30 days is common. Put a date on it rather than a number of days.