How to Size an Industrial Boiler: Steam Load, Pressure and TPH

Work out the steam load from your process, your heat load or the fuel you burn today, pick the working pressure, and choose a boiler size with sensible margin.

4 min read

By the Yantra Boilers team

The boiler sizing helper on a buyer's enquiry form, beside the Boiler Desk

Key takeaways

  • Size a boiler on the steam your process really uses at the pressure it needs, not on the old boiler's nameplate.
  • Three ways to estimate the load: add up the steam users, convert the heat load, or work back from the fuel you burn today.
  • Each kilogram of steam carries the steam's enthalpy at the working pressure minus the feed water's: about 604 kcal at 10.54 kg/cm² with 60 °C feed water.
  • Pick the next standard size with about 10% in hand; a much larger boiler runs at low load, cycles and wastes fuel.

Most boiler enquiries start with a number the buyer is not sure of. “We need a 2 ton boiler” may mean the old one was rated at 2 TPH, or that a consultant once said so, or that it sounds right. Sizing it properly takes an hour with the plant engineer, and it decides whether the boiler runs well for twenty years or wastes fuel from the first day.

This guide is for makers and buyers alike: three ways to estimate the steam load, how pressure and feed water change the answer, and how to choose the size.

Start from the steam the process uses

A boiler is sized for the steam the plant uses at its busiest steady hour, at the pressure the process needs. There are three ways to get there, and a careful engineer uses at least two and checks they agree.

1. Add up the steam users

List every piece of equipment that takes steam: cookers, dryers, jacketed kettles, autoclaves, presses, heat exchangers, tracing. Their makers usually state steam consumption in kg/hr. Add them up for the equipment that runs at the same time, not for everything on the floor, and add line losses and blow-down.

2. Convert the heat load

If the process load is known as heat, in kcal/hr, divide it by the heat each kilogram of steam delivers. That is the enthalpy of saturated steam at the working pressure minus the enthalpy of the feed water. From the steam table, steam at 10.54 kg/cm² (g) carries about 664 kcal/kg; feed water at 60 °C carries about 60. So each kilogram delivers about 604 kcal.

Heat loadHeat per kg of steamSteam needed
12,00,000 kcal/hrabout 604 kcal/kgabout 1,985 kg/hr
At 10.54 kg/cm² (g) working pressure and 60 °C feed water.

3. Work back from today's fuel

A plant replacing an old boiler usually knows its fuel bill better than its steam load. Multiply the fuel burned per hour at full load by its calorific value and the boiler's efficiency, and divide by the heat per kilogram of steam. A plant burning 525 kg of rice husk an hour (about 3,200 kcal/kg) in a boiler running at 72% is making roughly 2,000 kg/hr of steam at 10.54 kg/cm².

Pick the working pressure

The working pressure is set by the process: the temperature it needs and the pressure drop to the farthest user. Higher pressure means hotter steam and smaller pipes, but a heavier boiler and a slightly lower heat per kilogram delivered at the user once the steam is let down. Do not specify a higher pressure than the process needs just because the old boiler had it.

Actual output and “from and at 100 °C”

Boiler capacities are often stated from and at 100 °C (F&A): the steam the boiler would make if the feed water were at 100 °C and the steam left at atmospheric pressure. The actual output at your pressure and feed water temperature is lower. To compare offers, convert: F&A rating = actual steam × heat per kg ÷ 539 (the latent heat at 100 °C). 2,000 kg/hr of actual steam at 10.54 kg/cm² with 60 °C feed is about 2,243 kg/hr F&A.

Choose the size

  • Take the steady peak load and add a margin of about 10% for fouling, fuel variation and future additions.
  • Pick the next standard size up. Makers build in steps: 1, 1.5, 2, 2.5, 3, 4, 5 TPH and so on.
  • Do not oversize by much. A boiler running at 30% load cycles, loses efficiency and wears faster.
  • If the load swings widely or the plant cannot stop, two smaller boilers can beat one large one.
  • Raising the feed water temperature with condensate return or an economiser reduces the load the boiler has to carry.

With the example above, about 1,985 kg/hr plus 10% is about 2,184 kg/hr, so a 2.5 TPH boiler is the sensible choice, rather than a 2 TPH running flat out or a 4 TPH running at half load.

Put it in the enquiry

Whichever side you are on, write the load, the pressure, the fuel and how you got the numbers into the enquiry. A maker who receives “2.5 TPH, 10.54 kg/cm², rice husk, from 525 kg/hr of husk today” can send a meaningful quotation the same day.

Common sizing mistakes

  • Copying the old boiler's rating without checking whether it was actual or from and at 100 °C.
  • Adding up every steam user on the floor as if all of them ran at once.
  • Forgetting blow-down, deaerator and line losses, which can add several per cent.
  • Choosing a pressure far above what the process needs, out of habit.
  • Ignoring the fuel: a boiler sized on dry husk struggles in the monsoon on wet husk.

Every enquiry form that asks for these numbers saves a round of calls. Buyers who are unsure can estimate from the fuel they burn today, and the maker's engineer confirms it on the first call.

The sizing helper on a boiler maker's enquiry form: estimate steam from the fuel burned today
The enquiry form's sizing helper, on a buyer's phone.

Frequently asked questions

What does TPH mean for a boiler?
Tonnes of steam per hour. 1 TPH is 1,000 kg of steam an hour, usually stated either as actual output at the working pressure or as from and at 100 °C.
How much margin should a boiler have?
About 10% over the steady peak load is a common rule. Much more makes the boiler run at low load, which wastes fuel and shortens its life.
Does feed water temperature matter?
Yes. Warmer feed water means less heat per kilogram of steam, so the same boiler makes more steam. Returning condensate is one of the cheapest ways to gain capacity.